On Nov 26th 2015, the commencement ceremony of Yinshan Multi-function Shaft Sinking Project of Jiangxi Copper Corporation was held at Dexing, Jiangxi Province. Representatives from the Client, Supervisor, China ENFI, JCHX Chief Engineer Mr. Honghui Li, VP of JCHX Shaft Branch, Mr. Guangzhang Lu attended the ceremony. Project Manager Mr. Feng Chen gave a opening speech in which he announced the commencement of the project and JCHX would undertake the works for total construction period of 1090 days. The shaft is 925m in depth, total excavation of 55724m³ total underground support of 12417m³, making it one of the major contracts for shaft sinking branch this year.