In November 2019, monthly output achieved 105,300 tons at Huanggang Project, which was an unprecedented record and marked a completion of annual target ahead of schedule.
In 2019, production was suspended for one month due to accident from third party and explosives supply was cut off for 14 days due to national holidays, however Huanggang Project overcame all difficulties by effective construction planning and cost reduction, facilitating a successful completion of annual production target and even ahead of time.
In November, we planned more work quantities after discussion with client; prompt maintenance and services for equipment was ensured to minimize impact on schedule; safety hazards were strictly controlled to avoid any risks; logistics assistance were provided to ensure front-line workers can have fresh meals on time and even underground.
Under the concerted efforts by all members, Huanggang Project not only overfulfilled monthly target but achieved the annual target in advance.