As a pilot program of using trackless equipment, Wuqia Project created a new record with single month lateral development of 431.9 m (5763.5 m3) in August after its previous record of 343m in April with No.3 Boomer 281.
In the past eight months, Wuqia Project has been working really hard despite of the harsh environment on plateaus, the main reasons for achieving this record in Wuqia Project are excellent management and high attention from the leadership, hard united and continuous contributions from all crew, good maintenance and timely repairing of equipment, smooth transportation of labors and good food supply by the support crew, strong and well organized policies and operation systems. We believe Wuqia Project shall continue to be the role model for other domestic projects and shall achieve more in the future.