Jinchuan Project Completed Works on 1450ml Successfully

On April 12th 2016, mining operations at low-grade ore body of Jinchuan Project – B Section at 1405ml was completed and accepted by the client successfully.

The works commenced on 25th Oct 2012, including up-cast ventilation drift, back fill drilling accesses, auxiliary shaft station, up-cast transverse drift. The acceptance was led by Project Management Director of Jinchuan Group – Mr. Guangyong Bai, attended by representatives from construction unit, engineering company, supervisor, contractor. The work group conducted site inspection and final acceptance meeting, during which the work quality was checked by the group, and reports from contractor, supervisor were reviewed. The consensus among all participants is that the works were completed in strict accordance with designs and requirements, meeting all quality standards. In light of this, the works at 1450ml was completed successfully subject to the contract.