On 5th Aug 2016, Yunnan Diqing Non-ferrous Metals Co Ltd held (hereinafter referred to as Diqing)“Mission Impossible” evaluation, Pulang Copper Mine Project contracted by JCHX Mining Management Co Ltd was awarded by the Client and Mr. Qingtian Gong – Vice President for JCHX and Chief Engineer for the Project received bonus valued RMB 110,000.00 on behalf of JCHX.
“Mission Impossible” is the competition organized by Command Office for Pulang Copper Mine of Diqing, for the purpose of stimulate all construction units to vigorously work together and meet annual target. The evaluation criteria were stipulated by the command office and the evaluation was done strictly in accordance to the Action Plan for“Mission Impossible”of First Phase Mining Production in Pulang Copper Mine. On 1st June 2016, the Command Office along with Supervision Unit conducted work acceptance on site, and convened the evaluation meeting on 8th June.
Sinking & Driving Engineering for the Third Section contracted by JCHX was completed timely according to the construction plan, which was awarded by RMB 30,000; meanwhile underground development of tunnel for tailing & backwater haulage achieved 120m per month target, tunnel exit was completed on May 24th , the preparation and tunnel development of 12.9m were all completed within 8 days, which met the key time-lines, thus being awarded with another RMB 80,000.