On 27 Apr 2020, good news came in succession: target of monthly output overfulfilled in terms of both blasted ore and extracted ore at Huibaoling Project.
Despite of significant impact by COVID-19 epidemic, Huibaoling Project timely conducted prevention works to keep everything under control which paved the way for work resumption subsequently.
In April, outstanding achievement was made through earnest endeavor from all project members with a total blasted ore of 278,012t, including 274,495t from stope and by-product of 3,517t. Both blasted ore and extracted ore exceeded monthly target while breaking records.
Notwithstanding shortage of manpower and materials, drilling crew managed to achieve 118.3m per month for the extension of main decline, which ranked the highest development record ever since. In the meantime, both excavation drilling and production drilling overfulfilled monthly targets.
More exciting news include the successful recovery of payment due from Jan to April and the honor of “Pioneer in Production” granted by the Client for March and April.
Leaders from Huibaoling Iron Mine Company highly acknowledged the achievements and hard work from JCHX and appreciated our efforts made both in production and epidemic prevention despite all difficulties.